Question: Chapter + 6 + Schedule Chapter 6 Exercise Name: Using the following information, develop an AON project network. Complete the forward and backward pass, compute
ChapterSchedule
Chapter Exercise
Name:
Using the following information, develop an AON project network. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Answer the following questions:
What is the critical path?
How many weeks to complete?
What is the slack for activity C For activity F
tableActivityPredecessor,Time WeeksANone,BACADBEC DFDGE F
tableESIDEFSLLSDUR,LF
Directions:
Place the activities in the proper order.
Add arrows between boxes.
Calculate the Early Start Dates type over ES in each box
Calculate the Early Finish Dates type over the EF in each
box
Calculate the Late Finish Dates type over the LF in each box
Calculate the Late Start Dates type over the LS in each box
Calculate the Slack for each activity type over the SL in each box
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock