Question: Chapter 7 Exercise 3 3. Variances for direct materials and direct labor Banner Company manufactures flags of various countries. Each flag has a standard of
Chapter 7 Exercise 3 3. Variances for direct materials and direct labor Banner Company manufactures flags of various countries. Each flag has a standard of eight square feet of fabric and three hours of direct labor time. Information about recent production activity follows. Actual cost of fabric: $4.50 per square foot Fabric consumed: 32,080 square feet Standard price per square foot of fabric: $4.25 Standard direct labor rate: $10.00 per hour Actual direct labor rate: $10.20 per hour Actual labor hours worked: 11,940 Actual production completed: 4,000 flags a. Compute the materials price variance and the materials quantity variance. b. Compute the labor rate variance and the labor efficiency variance
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts