Question: (Chapter 7 Process Interruptions ) Aquatica makes underwater camera housings for divers. The process begins with a solid rectangular block of aluminum that is used
(Chapter 7 Process Interruptions ) Aquatica makes underwater camera housings for divers. The process begins with a solid rectangular block of aluminum that is used to make a single housing. A Computer Numerically Controlled (CNC) machine drills into the block to make the metal frame of the housing. The CNC machine requires a 45-minute setup time before the production of a batch can begin. Each block requires 15 minutes of drilling on the CNC machine. The frame is then chemically treated in a series of baths. There is unlimited capacity in the treating stage. Finally, a worker must manually attach the various buttons and components to the metal housing. This assembly takes 120 minutes per housing per worker and Aquatica has 6 workers trained to do this task. Assume unlimited demand. The process is shown below. Also, assume there is a buffer inventory between the stages of the process.
Drilling on CNC machine ===> Chemical Treatment====> Assembly
Question 1
Suppose the process is supply constrained and operates with batches of 38 housings, what is the average inventory of housings?
Group of answer choices
6.2 units
3.7 units
4.8 units
8 units
Question 2
What batch size would yield a CNC drilling capacity equal to the assembly capacity? (Hint: find first the assembly capacity)
Group of answer choices
20 housings
15 housings
4 housings
9 housings
Question 3
If the batch size is 38 housings, what would be the CNC's approximate capacity (in housings per hour)?
Group of answer choices
10 housings per hour
8 housings per hour
4 housings per hour
16 housings per hour
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts