Question: Chapter 9 Question 11 a. the standard deviation of demand during the 8-week lead time is _______ pints. b. The average demand during the 8
Chapter 9 Question 11

a. the standard deviation of demand during the 8-week lead time is _______ pints.
b. The average demand during the 8 week lead time is _______ pints.
c. The reorder pain that results in a cycle service level of 96 percent is _______ pints.
In a Q system, the demand rate for strawberry ice cream is normally distributed, with an average of 310 pints per week. The lead time is 8 weeks. The standard deviation of weekly demand is 16 pints. Refer to the standard normal table for z-valuesStep by Step Solution