Question: Chapter 9 Reducing Project Duration 327 7. Use the information contained below to compress one time unit per move using the least cost method. Assume
Chapter 9 Reducing Project Duration 327 7. Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $2,000 and there is a savings of $100 per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. Plot these costs on a graph. What is the optimum cost-time schedule for the project? Note: The correct normal project duration and total direct cost are provided
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
