Question: Chassis 2 : 6 5 JPH , Station 2 9 : 0 sec / hr , Station 3 0 : 0 sec / hr ,

Chassis 2: 65 JPH, Station 29: 0 sec/hr, Station 30: 0 sec/hr, Station 31: 10 sec/hr, Station 32: 160 sec/hr, Station 33: 2 sec/hr, Station 34: 5 sec/hr, Station 35: 3 sec/hr.
If we automate Chassis 2 and improve the SAJPH output by 20%, what percent improvement would we expect to see at the Paypoint?
b) What would be new SAJPH of Chassis 2??
c) Why would we not see the Full Benefit of this potential improvement in Chassis 2?
d) Where would be the new Bottleneck? Where would it be??