Question: Check my work 7 Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations

Check my work 7 Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) 10 points Project Z Time: Cash flow: 1 $630 2 $760 3 $930 4 $580 5 $380 -$2,400 Skipped PI eBook Hint Print References Should the project be accepted or rejected? accepted O rejected