Question: Check out the project data for a Tik Tok enhanced app in the table below, then construct an AON to allow you to answer the
Check out the project data for a Tik Tok enhanced app in the table below, then construct an AON to allow you to answer the question below it.
| Activity | Duration (days) | Immediate Predecessors |
| A | 8 | - |
| B | 9 | - |
| C | 8 | B |
| D | 11 | A |
| E | 6 | A |
| F | 6 | B |
| G | 5 | C |
| H | 4 | C |
| I | 5 | F, G, H |
| J | 2 | D, E, I |
If you were to start on this project, which are the activities that you could start on at the very beginning of the project?
Select one:
a. A only
b. B only
c. A, B
d. None of these choices are correct.
e. D because it has the longest processing time
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts