Chegg.com
GMS 450 Assignment 2- Group
chegg.con
Iment/d/101bzrwhs9to55h74r32JgxDncGJqkn6FYV66VMX1HXA/edit
5st Plagiarism Checker...
Browse Malayalam...
SOAP2DAY
Citation
Help
Times ...
12
+
B
I
u?
A
3
5
6
2. What is the minimum expected time in which this project can be completed? The critical path is A-C-D-E-F-J-K given 37 weeks, as shown in Question 1.
\table[[Task,Expected Time (in weeks),Crash Time (given in Exhibit 2),\table[[Expected Time],[Crash Time]]],[A,3,3,0],[B,7,6,1],[C,6,5,1],[D,7,6,1],[E,9,8,1],[F,5,4,1],[G,6,4,2],[H,4,3,1],[I,2,2,0],[J,4,5,-1],[K,3,2,1]]
Minimum Expected Time = Critical path - Maximum time reduction on critical path
Minimum Expected Time =37-0-1-1-1-1-(-1)-1=33 weeks
Therefore, the minimum expected time in which this project can be completed is 33 weeks.
The probability that the project can be completed within 33 weeks is
Search
 Chegg.com GMS 450 Assignment 2- Group chegg.con Iment/d/101bzrwhs9to55h74r32JgxDncGJqkn6FYV66VMX1HXA/edit 5st Plagiarism Checker...

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!