Question: Chief Alright. We need to start immediately, no time for delay. Use Monday July 8 , 2 0 2 4 , as a starting point
Chief
"Alright. We need to start immediately, no time for delay. Use Monday July as a
starting point"
Bubba
"Bossman, do we need to work weekends and holidays to knock this thing out? I have some
things planned for the weekends coming up and Labor Day.."
Chief
No we don't need to extend resources for that. No weekends or holidays, standard day
work week should do it Well, we will certainly have to start with SITEWORK, and this will
take days probably"
Bubba
"After that, the UNDERGROUND UTILITIES can start, and I know we can knock those out in
days"
Larry
"Since we are talking about the outside work, we would have to include days for
LANDSCAPING before we CLOSEOUT THE PROJECT"
Chief "Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is complete"
Bubba "Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!"
Larry "How much time will we need for EXTERIOR PAINTING?"
Chief days"
Larry "Okay, but we will have to complete the EXTERIOR SIDING and FINISH ROOF before then"
Chief
"Yep, but let's get back to the beginning. The ROUGH PLUMBING should take days, and
needs to start days after FORMPOUR SLAB starts which will take at least days to
complete"
Bubba
Do we have to wait until the UNDERGROUND UTILITIES are complete before we
FORMPOUR SLAB?"
Chief
No FORMPOUR can start right after SITEWORK, and we will have to wait until the slab is
complete before starting to FRAME WALLS"
Larry
"FRAME WALLS is crucial, let's put days for that. Its completion allow ROUGH ELECTRIC,
FRAME ROOF, and the WINDOWSDOORS to start"
Chief
"Okay, so let's say days for ROUGH ELECTRIC, days to hang WINDOWSDOORS and the
carpenters can FRAME ROOF in days"
Bubba
If the boys can frame the roof in days, surely the roofers can FINISH ROOF right after
that in days as well"
Chief
"Yep, FRAME ROOF will allow ROUGH MECHANICAL to start, which will take every bit of
days. ROUGH MECHANICAL cannot start until the UNDERGROUND UTILITIES are done
either"
Larry
"EXTERIOR SIDING can start after the WINDOWSDOORS and should take days to
complete"
Chief
"Slow down boys, make sure you don't start the days worth of DRYWALL until ROUGH
MECHANICAL is complete, and Bubba make sure they complete the FINISH ROOF first
before DRYWALL starts this time!"
Bubba Boss"
Larry
"INSULATION might take days, but needs to wait on ROUGH ELECTRIC, ROUGH
MECHANICAL, and ROUGH PLUMBING to be complete before starting, but should be
complete before DRYWALL is complete
Chief
We need to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND
UTILITIES"
Bubba
"Great, so let's have days for FINISH ELECTRIC, and days each for FINISH PLUMBING, and
FINISH MECHANICAL, and know that all three need DRYWALL to be complete before
starting"
Chief
"Correct, but don't forget about INTERIOR PAINT, which needs days to complete, and
needs to happen after DRYWALL and before FINISH ELECTRIC"
Larry
"That should do it Make sure that we have days for PROJECT CLOSEOUT after the
FINISH MEP activities and LANDSCAPING to tie up any loose ends"
Chief "Sounds good. Great work boys!"
I need it with the AON Diagram t
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock