Question: Chief Alright. We need to start immediately, no time for delay. Use Monday July 8 , 2 0 2 4 , as a starting point

Chief
"Alright. We need to start immediately, no time for delay. Use Monday July 8,2024, as a
starting point"
Bubba
"Bossman, do we need to work weekends and holidays to knock this thing out? I have some
things planned for the weekends coming up and Labor Day.."
Chief
"No, we don't need to extend resources for that. No weekends or holidays, standard 5 day
work week should do it. Well, we will certainly have to start with SITEWORK, and this will
take 7 days probably"
Bubba
"After that, the UNDERGROUND UTILITIES can start, and I know we can knock those out in
12 days"
Larry
"Since we are talking about the outside work, we would have to include 7 days for
LANDSCAPING before we CLOSEOUT THE PROJECT"
Chief "Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is complete"
Bubba "Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!"
Larry "How much time will we need for EXTERIOR PAINTING?"
Chief "5 days"
Larry "Okay, but we will have to complete the EXTERIOR SIDING and FINISH ROOF before then"
Chief
"Yep, but let's get back to the beginning. The ROUGH PLUMBING should take 12 days, and
needs to start 5 days after FORM/POUR SLAB starts , which will take at least 7 days to
complete"
Bubba
"Do we have to wait until the UNDERGROUND UTILITIES are complete before we
FORM/POUR SLAB?"
Chief
"No, FORM/POUR can start right after SITEWORK, and we will have to wait until the slab is
complete before starting to FRAME WALLS"
Larry
"FRAME WALLS is crucial, let's put 5 days for that. Its completion allow ROUGH ELECTRIC,
FRAME ROOF, and the WINDOWS/DOORS to start"
Chief
"Okay, so let's say 7 days for ROUGH ELECTRIC, 6 days to hang WINDOWS/DOORS and the
carpenters can FRAME ROOF in 7 days"
Bubba
"If the boys can frame the roof in 7 days, surely the roofers can FINISH ROOF right after
that in 3 days as well"
Chief
"Yep, FRAME ROOF will allow ROUGH MECHANICAL to start, which will take every bit of 5
days. ROUGH MECHANICAL cannot start until the UNDERGROUND UTILITIES are done
either"
Larry
"EXTERIOR SIDING can start after the WINDOWS/DOORS, and should take 6 days to
complete"
Chief
"Slow down boys, make sure you don't start the 6 days worth of DRYWALL until ROUGH
MECHANICAL is complete, and Bubba - make sure they complete the FINISH ROOF first
before DRYWALL starts this time!"
Bubba "10-4 Boss"
Larry
"INSULATION might take 3 days, but needs to wait on ROUGH ELECTRIC, ROUGH
MECHANICAL, and ROUGH PLUMBING to be complete before starting, but should be
complete before DRYWALL is complete "
Chief
"We need to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND
UTILITIES"
Bubba
"Great, so let's have 4 days for FINISH ELECTRIC, and 5 days each for FINISH PLUMBING, and
FINISH MECHANICAL, and know that all three need DRYWALL to be complete before
starting"
Chief
"Correct, but don't forget about INTERIOR PAINT, which needs 4 days to complete, and
needs to happen after DRYWALL and before FINISH ELECTRIC"
Larry
"That should do it! Make sure that we have 2 days for PROJECT CLOSEOUT after the 3
FINISH MEP activities and LANDSCAPING to tie up any loose ends"
Chief "Sounds good. Great work boys!"
3 I need it with the AON Diagram t

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!