Question: Choices: A) Week 5: 70, Week 7: 40 B) Week 6: 70, Week 8: 40 C) Week 5: 70 D) Week 6: 95, Week 8:
Choices:
Use the information below to answer this question. First using MRP chart, develop the schedule then select your answers. The planned-order release for product A is: Given the following information, develop a material requirements plan for end item A and its components. 95 and 40 units of A are needed at the beginning of week 6 and 8, respectively. Item On-Hand On-Order Lead Time Order Size 1 wk lot-for-lot 25 20 (wk 2) 1 wk lot-for-lot 2 wks lot-for-lot 100 1 wk 100 2 wks 200 B(3) C(2) F(2) The planned-order release for product A is
A) Week 5: 70, Week 7: 40
B) Week 6: 70, Week 8: 40
C) Week 5: 70
D) Week 6: 95, Week 8: 40
E) Week 5: 95, Week 7: 40