Question: Choose a statement that is NOT true. When accelerating the schedule, you should pay less amount for indirect costs. Accelerating an activity ( reducing activity

Choose a statement that is NOT true.
When accelerating the schedule, you should pay less amount for indirect costs.
Accelerating an activity (reducing activity duration) incurs increased direct activity cost.
The path with the longest duration becomes the critical path.
In accelerating the schedule, the first activity to reduce its duration is that with the highest daily cost.