Question: Choose the correct Answer A project manager is discussing with the project management office the implementation of risk audits in the project. What should be
Choose the correct Answer
A project manager is discussing with the project management office the implementation of risk audits in the project. What should be the purpose of risk audit?
a A risk audit gives the opportunity to verity the completeness of the risk register and risk report.
b A risk audit gives the opportunity to validate the existence of a risk management plan.
c A risk audit gives the opportunity to consider the effectiveness of the risk management response strategy
d A risk audit gives the opportunity to consider the effectiveness of the entire risk management process