Question: Choose the correct Answer A project manager is discussing with the project management office the implementation of risk audits in the project. What should be

Choose the correct Answer
A project manager is discussing with the project management office the implementation of risk audits in the project. What should be the purpose of risk audit?
a. A risk audit gives the opportunity to verity the completeness of the risk register and risk report.
b. A risk audit gives the opportunity to validate the existence of a risk management plan.
c. A risk audit gives the opportunity to consider the effectiveness of the risk management response strategy
d. A risk audit gives the opportunity to consider the effectiveness of the entire risk management process

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!