Question: Choose the correct answer: During MRP Scheduling, On-hand items should be better to A. allocate when first requirement of that item appears B. None C.
Choose the correct answer:
During MRP Scheduling, On-hand items should be better to
A. allocate when first requirement of that item appears
B. None
C. keep in inventory for future requirement
D. allocate during last requirement of that item appears