Question: Choose the correct option from those given below. The following table represents the manufacturing process of a small electrical appliance. The demand for the appliance

Choose the correct option from those given below.
The following table represents the manufacturing process of a small electrical appliance. The demand for the appliance is 630 units/day, and the average operating hours for the plant is 9 hour/day.
Task Task Time (sec) Precedence Relationship
A 40-
B 50 A
C 35 A
D 30 B
E 20 C
F 25 D
G 34 A
H 28 E, F
I 38 G, H
J 44 I
K 46 J
Total Time 390
What is the ideal cycle time?