Question: choose the correct project network diagram below begin{tabular}{ccc} hline Activity & Duration (days) & Predecessors hline A & 1.5 & None B &
choose the correct project network diagram below


\begin{tabular}{ccc} \hline Activity & Duration (days) & Predecessors \\ \hline A & 1.5 & None \\ B & 6 & None \\ C & 4 & None \\ D & 0.5 & A, B \\ E & 7.5 & C \\ F & 6.5 & D, E \\ G & 3.5 & F \\ H & 0.5 & F \\ \hline \end{tabular} UD. a