Question: Choose the correct statement A critical path presents the tatal duration of a project O The critical path identifies the tasks that must be used

Choose the correct statement A critical path
Choose the correct statement A critical path presents the tatal duration of a project O The critical path identifies the tasks that must be used to complete the project on schedule O the project An activity is said to be on the critical path if there is no lag time to push the activity date out without affecting the duration of