Question: Choose two correct requirements for obtaining a materialman's lien. ( Choose two correct answers ) Filing of a notice of lien within 1 0 days

Choose two correct requirements for obtaining a materialman's lien. (Choose two correct answers)
Filing of a notice of lien within 10 days after the last work performed
Sale of materials without reference to the improvement of specific real property
Verification of the notice of lien by an affidavit of the claimant
Filing of a notice of lien with a county official