Question: Chp 6 - 2 Saved ! Required Information [ The following information applles to the questlons displayed below. ] In 2 0 2 4 ,

Chp 6-2
Saved
!
Required Information
[The following information applles to the questlons displayed below.]
In 2024, the Westgate Construction Company entered Into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows:
\table[[,2024,2025,2026],[Cost incurred during the year,$2,044,000,$2,628,000,$2,890,800