Question: Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris's college

Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris's college instructor aside a paper due next week. Chris decided that she will prepare the paper on the new computer. She made a list of the activity she will need to do and they're estimated times.

a. Arrange the activities into two logical sequences.

b. (1) Construct an AOA network diagram.

(2) Construct an AON diagram.

c. Determine the critical path and the expected duration time.

d. What are some possible reasons for the project to take longer than the expected duration?

Estimated time (hrs): and Activity (abbreviation)

0.8 install software (Inst) 0.4 Outline the paper (Out) 0.2 Submit paper to the instructor (Sub) 0.6 Choose a topic (Sub)

0.5 Use grammar-checking routine and make corrections (Ck) 0.3 Write the paper using the word-processing software (Write)

2.0 Shop for a new computer (Sh) 1.0 Select and purchase computer (Sel) 2.0 Do Library research on chosen topic (Lib)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!