Question: Circular logic is created and identified when: Select the correct option. There is no predecessor or successor relationship An activity finishes before it starts An
Circular logic is created and identified when:
Select the correct option.
There is no predecessor or successor relationship
An activity finishes before it starts
An activity's logic ties its successors back to its predecessors
The project start date is after the data date