Question: Clark Howard considers himself a conservative project manager, so he never accepts deadlines that provide a safety margin below 8 5 % . The Project
Clark Howard considers himself a conservative project manager, so he never accepts deadlines that provide a safety margin below The Project Management software used by your company estimates a new project has an average duration of weeks and a standard deviation of weeks. Given Clark's assumption, what would the most appropriate duration for the project be