Question: Class Assignment # 2 Chapter 6 1 . Draw a project network from the following information. What activity ( s ) is a burst activity?

Class Assignment #2 Chapter 6
1. Draw a project network from the following information. What activity(s) is a burst activity? What
activity(s) is a merge activity?
2. Draw a project network from the following information. What activity(s) is a burst activity? What
activity(s) is a merge activity?
3. Draw a project network from the following information. What activity(s) is a burst activity? What
activity(s) is a merge activity?
Class Assignment #2 Chapter 6
4. Draw a project network from the following information. What activity(s) is a burst activity? What
activity(s) is a merge activity?
5. From the following information, develop an AON project network. Complete the forward and
backward pass, compute activity slack, and identify the critical path. How many days will the
project take?
6. The project information for the custom order project of the Air Control Company is presented
here. Draw a project network for this project. Compute the early and late activity times and the
slack times. Identify the critical path.
Class Assignment #2 Chapter 6
7. You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for
completing the project within 7 working days. The contract also contains a penalty clause in which
you will lose $100 for each day the project takes longer than 7 working days.
Draw a project network given the information below. Complete the forward and backward pass,
compute the activity slack, and identify the critical path. Do you expect to receive a bonus or a
penalty on this project?
ID DESCRIPTION PREDECESSOR
TIME
(DAYS)
A Prepare site NONE 2
B Pour foundation A 3
C Erect frame B 4
D Roof C 4
E Windows C 1
F Doors C 1
G Electrical D E F 3
H Rough in frame F G 2
I Door opener H 1
J Paint I 2
K Cleanup J 1
8. You are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a
project network given the information below. Complete the forward and backward pass, compute
activity slack, and identify the critical path.
How long will this project take? How sensitive is the network schedule? Calculate the free slack
and total slack for all noncritical activities.
Class Assignment #2 Chapter 6
9. K. Nelson project manager of Print Software, Inc., wants you to prepare a project network;
compute the early, late, and slack activity times; determine the planned project duration; and
identify the critical path. His assistant has collected the following information for the Color
Printer Drivers Software Project:
10. A large southeast city is requesting federal funding for a park-and-ride project. One of the
requirements in the request application is a network plan for the design phase of the project.
Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this
requirement. She has gathered the activity time estimates and their dependencies shown here.
Show your project network with the activity early, late, and slack times. Mark the critical path.
Class Assignment #2 Chapter 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!