Question: Class Problem [ 4 0 pts ] | teams of up to 4 ] A manufacturing line consists of 4 separate processes. The arrival mean
Class Problem ptsteams of up to
A manufacturing line consists of separate processes. The arrival mean is based on Takt time. Assume no scrap, blocking, transport times, setup times. All times in minutes.
Which operation is the main bottleneck process for the line? Is variability increased or decreased downstream from it Explain the rationale for your answer.
pts Calculate and for You may use the spreadsheet to confirm, but must show work.
pts It is desired to reduce flowtime and WIP for the system significantly. There are four alternatives, each of approximately equal cost:
a OP and OP positions can be swapped on the line
b The processing time standard deviation of can be reduced by
c OP processing time can be reduced to
d The MTTF of OP can be extended to hours.
Which option should be selected? Justify your answer. Use the spreadsheet.
Love Purple
Dequitment of Merturieat and Industrial Inginecting
Lean Mernufacturing Systeins ID
LOVE PURPLE
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock