Question: CleanTech Solutions, an environmental consultancy, needs to analyze its project costs based on project hours. Data Collected: Project A: Total Costs: $50,000, Hours Worked: 500
- CleanTech Solutions, an environmental consultancy, needs to analyze its project costs based on project hours.
- Data Collected:
- Project A: Total Costs: $50,000, Hours Worked: 500
- Project B: Total Costs: $80,000, Hours Worked: 800
- Tasks:
- Use the High-Low Method to determine the variable cost per hour and fixed costs.
- Develop a cost equation.
- Predict costs for a project requiring 1,000 hours.
- Analyze the cost-effectiveness of hiring additional consultants.