Question: clearer image, thanks for the help You are creating a database for the Oklahoma City Thunder NBA basketball team. Given the project network that follows,

You are creating a database for the Oklahoma City Thunder NBA basketball team. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path Use this information to create a Gantt chart for the project mo Der Det To DURU What are the critical activities? What is the slack for C? What is the slack for D? What is the slack for E? What is the slack for F? What is the length of the project? time periods. A Problem Definition B System Analysis C Design 10 D Design Database E Develop Input Screens F Develop Output Reports G Create Database HTest System Implement System Legend ESID EF SLK LS DUR LE E A B H 6 D G 7