Question: Click Submit to complete this assessment Question 53 Examine the following network diagram with activities (tasks) and their durations in days for a small project
Click Submit to complete this assessment Question 53 Examine the following network diagram with activities (tasks) and their durations in days for a small project and awes the related questions below: Network Diagram Required (4 marks) 1. Which path is the critical path? 2. How long is the critical path? 3. What is the schedule duration for this project? 4. What is the overall effort for this project? Arial 3 (12pt) - T TTTT Paragraph % DOO fx Mashups - CE w 0 Click Submit to complete this assessment Question 53 Examine the following network diagram with activities (tasks) and their durations in days for a small project and awes the related questions below: Network Diagram Required (4 marks) 1. Which path is the critical path? 2. How long is the critical path? 3. What is the schedule duration for this project? 4. What is the overall effort for this project? Arial 3 (12pt) - T TTTT Paragraph % DOO fx Mashups - CE w 0
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts