Question: Clients are served in a process with two resources (workers in each resource work independently). The processing time (per worker) of the first resource is
Clients are served in a process with two resources (workers in each resource work independently). The processing time (per worker) of the first resource is 13 minutes. The processing time (per worker) of the second resource is 4 minutes. The first resource has 3 workers and the second resource has 3 workers. Assume 3 workers are added to the process and all of them are assigned to one of the resources.
What would be the capacity of this process?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.