Question: Clients are served in a process with two sequential resources. The processing times for the resources are 0 . 4 2 and 0 . 3

Clients are served in a process with two sequential resources. The processing times for the resources are 0.42 and 0.38 hours.
Instruction: Round your answer to 2 decimal places.
What is the capacity of this process in terms of clients per hour? clients per hour
 Clients are served in a process with two sequential resources. The