Question: Clients are served in a process with two sequential resources. The capacities of the resources are 1.2 and 1.3 clients per minute What is
Clients are served in a process with two sequential resources. The capacities of the resources are 1.2 and 1.3 clients per minute What is the capacity of this process in terms of clients per minute? Note: Round your answer to 3 decimal places. Capacity in terms of clients per minute
Step by Step Solution
3.40 Rating (150 Votes )
There are 3 Steps involved in it
Solution Since the first ressource has a capacity of 12 clients per minute and ... View full answer