Question: CM 1 1 0 : In - Class Exercise # 1 Information: You have received an request for proposal ( RFP ) to complete the

CM 110: In-Class Exercise #1
Information:
You have received an request for proposal (RFP) to complete the concrete portion of a slab on grade for a residence in northern Colorado. You will be responsible for providing and installing a 6 mil . vapor barrier, pouring and finishing a concrete slab using 2500 psi concrete.
The slab has the following dimensions: 25'40'4''
Keep it simple: Don't worry about turning down/overlapping the vapor barrier, etc. Just use straight floor area (25'40') for the calculations.
You are NOT responsible for reinforcing, pour-break material or formwork.
Materials:
6 mil. vapor barrier -100' by 10' roll - $65
2500 psi concrete - $105CY(includes delivery and placement)
2540412~~333.3327=12.33
Laborer installing vapor barrier - Hourly rate $16hr, productivity rate 500 SF ,
Laborer placing concrete - Hourly rate $20? hour, productivity rate 10CYhr
Laborer finishing concrete - Hourly rate $20? hour, productivity rate 250 SF/hr
How many CY of concrete are required to complete the slab on grade?
12.33 cy
Since unit cost has been provided ($CY), what is the total material cost for the concrete?
12.33105~~$1294.65
How many square feet of vapor barrier are required?
1000 sf
What is the total material cost for the vapor barrier?
$65
What is the square footage of concrete slab that must be finished?
1000sf
What is the unit cost ($/SF) for labor to install the vapor barrier?
161i1hr500=
What is the unit cost ($CY) for labor to place the concrete?
What is the unit cost ($SF) for labor to finish the concrete?
CM 1 1 0 : In - Class Exercise # 1 Information:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!