CMIT Level 2
In a Design-Build contract, quailty assurance involves reviewing the ___ to make sure that___.
- contractor's quality control practices; quality control is being implemented
- Project's specifications; cost overruns and schedule delays do not occur
- projects finished work; the work matches the drawings
- architects designs; the architech is implementing quailty control