Question: CNST 3 3 3 1 Earned Value question handout ( This sheet is not graded; please record all your answers in the Blackbaord. ) Question
CNST Earned Value question handout This sheet is not graded; please record all your answers in the Blackbaord. Question Perform Earned Value analysis for the following project. Physical completion and actual cost information is provided to you by crew supervisors based on actual field progress. Status date is at the end of the Second month. Answer questions in the Blackboard. BCWS: Budget Cost Work Scheduled value work should have completed by the status date BCWP: Budget Cost Work Performed Physical completion Baseline cost S value work actually completed ACWP: Actual Cost Work Performed This is a user input of S actually spend BAC: Budget at Completion EAC Estimated cost At Completion BACCPI of the overall project SVBCWPBCWS SPIBCWPBCWS CVBCWPACWP CPIBCWPACWP Month Month Month mon Task B D E F Physical compelet Duration after mon. Baseline cost Actual cost Month mon $ $ $ $ mon $ $ mon $ $ mon $ $ mon $ $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
