Question: ( CO 3 ) In evaluating time - cost trade - offs, we start by crashing the task on the critical path that Group of

(CO 3) In evaluating time-cost trade-offs, we start by crashing the task on the critical path that
Group of answer choices
has the lowest cost to reduce by one unit of time.
has the lowest total crash cost.
can be reduced the most.
is the longest.
None of the above