Question: Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
| Activity | Description | Immediate Predecessor | Time (weeks) |
|---|---|---|---|
| A | Survey building site | 7 | |
| B | Develop initial design | 11 | |
| C | Obtain board approval | A, B | 16 |
| D | Select architect | C | 4 |
| E | Establish budget | C | 7 |
| F | Finalize design | D, E | 14 |
| G | Obtain financing | E | 12 |
| H | Hire contractor | F, G | 7 |
(a) Draw a project network.
(b) Identify the critical path. (Enter your answers as a comma-separated list.)
(c) Develop the activity schedule for the project.
(d) Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
The expected completion time is _____ weeks, which is ---Select--- less or greater than 1 year.
I really need help with this question thank you! I have already submitted twice and the answers are not fully correct.

(a) Draw a project network. (Submit a file with a maximum size of 1 MB.) No file chosen This answer has not been graded yet. (b) Identify the critical path. (Enter your answers as a comma-separated list.) (c) Develop the activity schedule for the project
Step by Step Solution