Question: Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded

Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin:
\table[[Activity,Description,\table[[Immediate],[Predecessor]],\table[[Time],[(weeks)]]],[A,Survey building site,-,6],[B,Develop initial design,-,7],[C,Obtain board approval,A, B,12],[D,Select architect,C,6],[E,Establish budget,C,7],[F,Finalize design,D,5],[G,Obtain financing,D, E,6],[H,Hire contractor,F, G,11]]
a. Which project network is correct?
(i)
(ii)
(iii)
(iv)
Network (i)
b. Identify the critical path.
B-C-E-G-H
c. Develop the activity schedule for the project. If your answer is zero, enter "0".
\table[[Activity,\table[[Earliest],[Start]],\table[[Latest],[Start]],\table[[Earliest],[Finish]],\table[[Latest],[Finish]],Slack,,\table[[Critical],[Activity]]],[A,,1,,,1,,No],[B,,,,,,,)
 Colonial State College is considering building a new multipurpose athletic complex

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!