Question: Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms and intramural facilities. The following activities would have to be undertaken before construction can begin:

A. Construct the Project Network using AOA (Activity-on-arrow) method. Using normal times and costs, compute the project duration using forward pass and backward pass. Plot also the critical path and identify the critical activities. What is the projects normal cost?
B. Specify what activities you will crash in order to shorten the project completion time by 4 weeks. Show your solutions. What is the resulting total project cost for a reduction of 4 weeks?
Activity ABCDEFGH Activity ABCDEFGH Description Survey building site Develop initial design Obtain board approval Select architect Establish budget Finalize design Obtain financing Hire contractor Time (weeks) Normal Crash 1 36254393 -3-33142 Immediate Predecessor A, B D, E E F, G Cost (S) Normal 900 2000 500 1800 1500 3000 8000 1000 Crash 1700 4000 1000 2400 1850 3900 9800 2000Step by Step Solution