Question: Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
ActivityDescriptionImmediate
PredecessorTime
weeksASurvey building siteBDevelop initial designCObtain board approvalA, BDSelect architectCEEstablish budgetCFFinalize designD, EGObtain financingEHHire contractorF, G
a
Identify the critical path drawing the project network would be helpful Be sure to use Capital letters!. Enter your answers as a commaseparated list.
ACEFH
b
Develop the activity schedule for the project.
ActivityEarliest
StartLatest
StartEarliest
FinishLatest
FinishSlackABCDEFGH
c
Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
The expected completion time is weeks, which is Selectlessgreater than year.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock