Question: Combinations! A company wants to develop a new layout for its production area for a new product. The total project consists of seven activities. The
Combinations!
A company wants to develop a new layout for its production area for a new
product. The total project consists of seven activities. The precedence
relationships and the time requirements of the tasks are given.
The duration of task is depending on the number of workstations that need to be
constructed. One should take days construction time per workstation. An
overview of the jobs that need to be done to assemble the new product is given.
Line Balancing
Additional information:
The jobs cannot be subdivided further.
The desired cycle time for the new product is given.
In case of using a parallel setup of workstations, an extra days for the construction of
switch points should be foreseen.
Also combination with 'Location' andor LP possible!
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock