Question: .com/cour 5 pts Question 15 Johnson Controls has a project with a cost of $7,000 and expected cash flow stream of $2,000 at the end
.com/cour 5 pts Question 15 Johnson Controls has a project with a cost of $7,000 and expected cash flow stream of $2,000 at the end of year 1, $3,000 at the end of year 2, and $5,000 at the end of year 3. At a discount rate (WACC) of 11.28%, what is the net present value (NPV) of this investment? Your answer should be between 580.00 and 1342.00, rounded to 2 decimal places, with no special characters. DQuestion 16 5 pts As c