Question: come, first - served rule, ( 2 ) earliest due date, and ( 3 ) critical ratio. Calculate the average lateness under each rule. Which
come, firstserved rule, earliest due date, and critical ratio. Calculate the average lateness under each rule. Which rule performs best?
Click the icon to view the job information.
The FCFS sequence is
gradgradgrad.
The average job lateness under the FCFS rule is
days. Enter your response rounded to two decimal places.
The EDD sequence is
The average job lateness under the EDD rule is
days. Enter your response rounded to two decimal places.
The CR sequence is
gradgrad
The average job lateness under the CR rule is
days. Enter your response rounded to two decimal places.
The
rule performs best.