Question: Companies must use the percentage-of-completion (overtime) method when estimates progresses toward completion are reasonably dependable. This statement is true or false? The most popular input
- Companies must use the percentage-of-completion (overtime) method when estimates progresses toward completion are reasonably dependable. This statement is true or false?
- The most popular input measure used to determine the progress toward completion is the cost-to-cost basis. This statement is true or false?