Question: Compare the following projects using the NPV method and the EAA method if the cost of capital is 18%. SHOW ALL WORK Year Project A
Compare the following projects using the NPV method and the EAA method if the cost of capital is 18%. SHOW ALL WORK
Year Project A Project B
0 ($500,000) ($500,000)
1. $175,000 $155,000
2 $225,000 $155,000
3 $300,000 $155,000
4 $200,000 $155,000
5 $155,000
6 $155,000
7 $155,000
8 $155,000