Question: Comparing known and expected capacity requirements with projected capacity availability is the job of: planned releases. load reports. lot sizing. work loading. time fencing.

Comparing known and expected capacity requirements with projected capacity availability is the job of:
planned releases.
load reports.
lot sizing.
work loading.
time fencing.
 Comparing known and expected capacity requirements with projected capacity availability is