Question: Competing demands and priorities, assessing risks, resource allocation, changes due to the uncertainty and complexity of the program scope, interdependencies among components, and the coordination

Competing demands and priorities, assessing risks, resource allocation, changes due to the uncertainty and complexity of the program scope, interdependencies among components, and the coordination of work to meet the program objectives is all part of the Program Integration Management as it pertains to decision making? Question 6Select one: True False