Question: Complete a network analysis chart for the following project assuming it should be finished as soon as possible. Your chart should show all the tasks

Complete a network analysis chart for the following project assuming it should be finished as soon as possible. Your chart should show all the tasks and their Earliest Start (ES), Duration (D), Earliest Finish (EF), Latest Start (LS), Latest Finnish (LF) and Float Time (FT). Identify critical path also

TASK

DURATION (DAYS)

CAN ONLY START AFTER

A

6

-

B

5

-

C

7

-

D

6

A, B

E

8

B

F

7

C

G

10

D, E, F

H

7

F

I

9

G

J

11

H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!