Question: Complete a network analysis chart for the following project assuming it should be finished as soon as possible. Your chart should show all the tasks
Complete a network analysis chart for the following project assuming it should be finished as soon as possible. Your chart should show all the tasks and their Earliest Start (ES), Duration (D), Earliest Finish (EF), Latest Start (LS), Latest Finnish (LF) and Float Time (FT). Identify critical path also
| TASK | DURATION (DAYS) | CAN ONLY START AFTER |
| A | 6 | - |
| B | 5 | - |
| C | 7 | - |
| D | 6 | A, B |
| E | 8 | B |
| F | 7 | C |
| G | 10 | D, E, F |
| H | 7 | F |
| I | 9 | G |
| J | 11 | H |