Question: Complete a Project Schedule network Diagram. Please use the numbers as activites Activity Immediate Predecessors Estimated Duration (Days) 1. - 3 2. - 4 3.
Complete a Project Schedule network Diagram. Please use the numbers as activites
| Activity | Immediate Predecessors | Estimated Duration (Days) |
| 1. | - | 3 |
| 2. | - | 4 |
| 3. | 1,2 | 1 |
| 4. | 3 | 5 |
| 5. | 3 | 8 |
| 6. | 4 | 5 |
| 7. | 5,6 | 1 |
| 8. | 7 | 8 |
| 9. | 7 | 10 |
| 10. | 8,9 | 2 |
| 11. | 10 | 2 |
| 12. | 11 | 15 |
| 13. | 11 | 10 |
| 14. | 11 | 6 |
| 15. | 12,13,14 | 2 |
| 16. | 15 | 6 |
| 17. | 15 | 4 |
| 18. | 15 | 4 |
| 19. | 16,17,18 | 1 |
| 20. | 19 | 4 |
| 21. | 19 | 2 |
| 22. | 20,21 | 1 |