Question: Complete an Activity-On-Node network diagram based on the scenario below. Scenario You're a member of a theater group and have been asked to prepare the
Complete an Activity-On-Node network diagram based on the scenario below.
Scenario
You're a member of a theater group and have been asked to prepare the schedule, etc. for a play scheduled for Christmas Eve service at one of the local churches in your hometown.
| Activity | Predecessor | Time (days) | ||
|---|---|---|---|---|
| Optimistic | Most Likely | Pessimistic | ||
| 1 | None | 2 | 4 | 6 |
| 2 | None | 5 | 5 | 5 |
| 3 | 2 | 3 | 5 | 7 |
| 4 | 1 | 7 | 10 | 13 |
| 5 | 1 | 11 | 12 | 13 |
| 6 | 2,4 | 5 | 6 | 7 |
| 7 | 3 | 9 | 10 | 11 |
| 8 | 3,6 | 5 | 7 | 9 |
| 9 | 4 | 7 | 9 | 11 |
| 10 | 5 | 3 | 3 | 3 |
| 11 | 7 | 15 | 17 | 19 |
| 12 | 8 | 6 | 8 | 10 |
| 13 | 9,10 | 7 | 8 | 15 |
| 14 | 7 | 12 | 14 | 16 |
| 15 | 12,13 | 16 | 17 | 18 |
Make sure you respond to each of the following five requirements.
- Construct an AON diagram using the process described in the videos.
- Calculate the estimated time for each activity using the three estimates provided.
- Determine the length of all paths and identify which path is the critical path.
- During the play, one of the activities on the critical path is delayed by one day. Is this serious?
- Qualitatively discuss the uncertainty of the critical path.