Question: Complete the chase production plan, using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you

Complete the chase production plan, using the following information. The only costs you need to consider here are layoff, hiring, and inventory costs. If you complete the plancorrectly, your hiring, layoff, and inventory costs should match those given here.

1st cost table:

Layoff Hiring Inventory Totals: 270 270 36,000 Costs: $405,000 $540,000 $72,000 Cost of plan: $1,017,000 Planning values Starting inventory: 3,000 Starting and ending workforce: 223 Hours worked per month per hour: 315 Hours per unit: 35 Hiring cost per worker: $2,000 Layoff cost per worker: $1,500 Monthly per-unit holding cost: $2

2nd cost table:

Month Forecasted sales March 1,728 April 1,719 May 1,179 June 927 July 1,890 August 2,313 September 2,475 October 2,709 November 3,249 December 3,357 January 2,799 February 2,457

Fill in the production plan table below (enter your responses as whole numbers).

Month

Forecasted sales

Sales in worker hours

to meet sales

average=248

Actual workers

Actual production

Layoffs

Hiring

Ending inventory

223

3,000

March

1,728

enter your response here(____)

enter your response here(___)

enter your response here(___)

enter your response here(___)

enter your response here(___)

enter your response here(___)

enter your response here(___)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!