Question: Complete the exercise below. You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, you review the schedule
Complete the exercise below.
You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, you review the schedule and costs. Based on your review,
- You should have spent $50,000 to date based on your initial plans and 100 days activities that were based on the schedule.
- You have actually spent $60,000 to date and completed activities for 110 days of the scheduled baseline, which should have cost $45,000 based on your initial plans.
- Budget required for the remaining work to be completed is estimated at $150,000.
Answer the following
PV (Planned Value) =
AC (Actual Cost) =
EV (Earned Value)=
ETC (Estimate to Complete) =
CPI =
SPI =
CV =
SV =
VAC (Variance at Completion) =
EAC (Estimate at Completion) =
TCPI =
Based on your earned value review, is the project under/over budget, behind/ahead of schedule and will the project be easy to complete with the current budget.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
