Question: Complete the exercise below. You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, you review the schedule

Complete the exercise below.

You are assigned to a project with an initial budget of $200,000 USD. Midway through the project, you review the schedule and costs. Based on your review,

  • You should have spent $50,000 to date based on your initial plans and 100 days activities that were based on the schedule.
  • You have actually spent $60,000 to date and completed activities for 110 days of the scheduled baseline, which should have cost $45,000 based on your initial plans.
  • Budget required for the remaining work to be completed is estimated at $150,000.

Answer the following

PV (Planned Value) =

AC (Actual Cost) =

EV (Earned Value)=

ETC (Estimate to Complete) =

CPI =

SPI =

CV =

SV =

VAC (Variance at Completion) =

EAC (Estimate at Completion) =

TCPI =

Based on your earned value review, is the project under/over budget, behind/ahead of schedule and will the project be easy to complete with the current budget.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!